Well 1 (producer) | Well 2 (injector) | ||
---|---|---|---|
Completion of drilling open hole | 4 June 2019 | Completion of drilling first section | 24 November 2019 |
Logging in reservoir section | 15 to 21 June 2019 | Construction of FO cable | 28 to 29 November 2019 |
Hydraulic testing | June and July 2019 | Cementing first section | 30 November 2019 |
Flowmeter logging | 10 July 2019 | Â | Â |
Wireline temperature log | 23 October 2019 | Â | Â |
Installation of FO cable | 24 to 31 October 2019 | Â | Â |
Cold water injection test 1 | 23 January 2020 | Â | Â |
Cold water injection test 2 | 22 February 2020 | Â | Â |