Skip to main content

Science – Society – Technology

Table 4 Financial model dialog for the geothermal well

From: Performance of geothermal power plants (single, dual, and binary) to compensate for LHC-CERN power consumption: comparative study

Recapitalization cost

Specified recapitalization cost

     

Calculated recapitalization cost includes drilling costs, pump costs, and surface equipment. When the reservoir temperature drops below an allowed minimum, new wells must be drilled and costs accounted for in the out years of the analysis

23,000,000$

     

Total capital cost

71,558,072$

     

Contingency (5%)

3,577,904$

     

Total direct cost

75,135,976$

     

Total installed cost

92,792,928$

     

Total installed cost per capacity

51,555$/kW

     

Indirect capital costs

% of direct cost

Non-fixed cost ($)

Fixed cost

Total cost ($)

  

Engineer, procure, construct

16

12,021,756

0

12,021,756

  

Project, land, miscellaneous

3.5

2,629,759

0

2,629,759

  

Sales tax of 5% applies to

80

–

–

3,005,439

  

Operation and maintenance cost

First year cost

Escalation rate (above inflation) (%)

    

Fixed annual cost

0

0

    

Fixed cost by capacity

70$/kW-yr

0

    

Variable cost by generation

3$/MWh

0

   Â