Table 3 Configuration specification dialog for the geothermal well

From: Performance of geothermal power plants (single, dual, and binary) to compensate for LHC-CERN power consumption: comparative study

Total production wells required % of confirmation wells used for production Number of confirmation wells Number of production wells to be drilled Ratio of injection wells to production wells Number of injection wells to be drilled
5.33897 50 1 4.33897 0.5 2.66949
Drilling and associated costs Cost multiplier Cost per well (USD) Number of wells Drilling cost (USD) Non-drilling cost (USD) Total cost (USD)
Exploration 0.5 770,910 2 1,541,819 750,000 2,291,820
Confirmation 1.2 1,850,183 2 3,700,367 250,000 3,950,367
Production Med 1,541,819 4.33897 6,689,914
Injection Med 1,541,819 2.66949 4,115,867
Surface equipment, installation 125,000 8.00846 1,001,058 1,001,058
Simulation cost 1,000,000 8.00846 8,008,460 8,008,460
Production and injection wells to be drilled 7.00846 10,805,780 250,000 11,055,780
Gross plant output 23,357.283 kW      
Cost 1800$/kW      
Power plant cost 42,043,108$      
Pump installation and casing cost 50$/ft Pump depth 2,859.928 ft Total cost 142,996.4$  
Pump cost 12,479.2$/hp Pump size 1345.62 hp Total cost 457,771$  
Number of pumps required 5.33897 Cost of pump 600,767$ Total cost 3,207,481$