Initial capital expenditures, 103 Euro | ||||
---|---|---|---|---|
Planning | 930 | Data Acquisition = 500 | Feasibility = 180 | Consultations = 250 |
Wells | 8114 | Site = 453 | Drilling = 6080 | Evaluation = 1581 |
Production pump | 632 | Pump setting depth = 612 m | El. power = 332 kW | |
Completion | 141 | Tubing, Power Cable = 99 | Pump installation = 42 | |
Heat exchanger | 894 | Area = 1828 m2 | Geoth. power = 5.5 MW | Geoth. work = 32.90 GWh |
Surface System | 606 | Piping, fittings, I&C = 536 | Filters, pressure vessels = 70 | |
Injection pump | 191 | El. power = 336 kW | ||
Peak load boiler | 1028 | Power = 15.7 MW | Peak load work = 8.2 GWh | |
Others | 1501 | Project management = 928 | Public relations = 400 | Power, data, insurances = 400 |
Total initial capital expenditure | 14,037 | |||
Euro Operating expenditures, 103 Euros p.a | ||||
Energy-/resource-related | 1006 | Electricity = 641 | Gas = 329 | Other = 36 |
Human resources | 489 | Human resources = 234 | Maintenance, Repair = 137 | Other = 118 |
Other (insurance, and public relations) | 137 | Liability ins. = 90 | Electronics, and machine breakdown ins. = 22 | Other = 25 |
Total initial operating expenditure | 1630 |